Analisa Pengaruh Manajemen Material Terhadap Produktivitas Kerja Pada Proyek Konstruksi Gedung Bertingkat Di Kota Palangka Raya

Analysis Of The Effect Of Material Management On Work Productivity In Multi-Storey Building Construction Projects In Palangka Raya City.

Authors

  • Putri Azzahra Universitas Muhammadiyah Palangkaraya
  • Rida Respati Universitas Muhammadiyah Palangkaraya

DOI:

https://doi.org/10.33084/mits.v12i2.7323

Keywords:

Manajemen Material, Produktifitas, Proyek, Regresi Linear Berganda, SPSS

Abstract

Material management plays an important role in the process of implementing construction projects because materials are the largest cost component in the process. Material management is carried out to support timeliness, quantity accuracy, and cost accuracy. One way to achieve timeliness, quality, and cost is by implementing good work productivity. Productivity becomes a measure in considering whether a project is carried out effectively or not. This study aims to determine what factors in material management affect the productivity of construction project work. The method used in this research is quantitative. Data analysis using multiple linear regression tests with the help of the SPSS 23.0 application. The results of this study obtained a multiple linear regression equation Y = (3.684) + 0.025X1 + 0.043X2 - 0.039X3 - 0.013X5 + 0.031X7. Where the material management factors that affect project work productivity in this study are material procurement planning and scheduling, project organization and personnel, purchasing materials according to planning, storage and warehouse, and control and supervision.

Downloads

Download data is not yet available.

Author Biographies

Putri Azzahra, Universitas Muhammadiyah Palangkaraya

Student of Civil Engineering, Universitas Muhammadiyah Palangkaraya

Rida Respati, Universitas Muhammadiyah Palangkaraya

Lecturer of Civil Engineering, Universitas Muhammadiyah Palangkaraya

References

Guerrero, Lilliana Abarca, and and Ana Grettel Leandro Hernandez. (2017). "Material Management Practices For Construction Waste Reduction." WIT Transaction on Ecology and The Environment, Vol, 223 1-7.

Hassan, Haekal, Jantje B. Mangare, and Pingkan A.K. Pratasis. (2016). Faktor-Faktor Penyebab Keterlambatan pada Proyek Konstruksi dan Alternatif Penyelesaiannya (Studi Kasus: di Manado Town Square III). Penelitian, Manado: Repository Universitas Sam Ratulangi.

Hudoyo, Citra Pradipta, and Ary Sismiani. (2022). "Analisis Pengaruh Kerja Lembur Terhadap Produktivitas Pekerja Konstruksi pada Proyek Pembangunan Gedung." Jurnal Ilmiah Multi Disiplin Indonesia Vol 1 No. 9 1306-1313.

Husnah, Doni Rinaldi Basri, and Defrison Nureb. (2017). "Pengaruh Manajemen Pengendalian Material dalam Mencegah dan Mengatasi Keterlambatan Proyek Bangunan di Madrasah Aliyah Kejuruan (MAK) Rokan Hulu." Jurnal Rab Construction Research, Vol. 2, No. 2 265-283.

Jonnaidi, Dwi Sartika. (2022). Analisis Produktivitas Tenaga Kerja dengan Metode Work Sampling. Skripsi, Pekanbaru: Universitas Islam Riau.

Jusoh, Zairra Mat, and Narimah Kasim. (2016). "A Review on Implication of Material Management to Project Performance." ENCON 2016 1-6. M, Ashika. 2019. "A Material Management in Construction Project Using Inventory Management System." Iconic Research and Engineering Journals Vol 3 Issues 5 52-58.

Madhavi, Phani T., Steve Varghese Mathew, and Roy Sasidharan. (2015). "Material Management In Construction - A Case Study." IJRET: International Journal of Research in Engineering and Technology 400-405.

Okolie, K.C., and Leona Mba. (2020). "Evaluation of Material Management Practices in Building Project in the FCT Abuja, Nigeria." Journal of Materials Science Research and Reviews, Vol. 6 No. 4 22-30.

Pranatawijaya, Viktor Handrianus, Widiatry, Ressa Priskila, and Putu Bagus Adidyana Anugrah Putra. (2019). "Pengembangan Aplikasi Kuisioner Survey Berbasis Web Menggunakan Skala Likert dan Guttman." Jurnal Sains dan Informatika, Vol 5 No. 2 128-137.

Sharafadeen, Olanrewaju, Oyebiyi Simeon, and Olatunya Deji Alfred. (2021). "Impacts and Awareness of Materials Management Strategies on Project Delivery in Nigerian Construction Industry." IJLRET Vol 07-Issues 09 56-64.

Suhardiyani, Putu Eny, I Putu Widyarsana, and Ni Kadek Sri Ebta Yuni. (2011). "Analisis Pengaruh Manajemen Material Terhadap Kualitas Kinerja Pelaksanaan Proyek Konstruksi Gedung di Kota Denpasar." Jurnal "MITSU" Vol. 10; No. 1 41-52.

Syafei, M. Yani, Iyan Andriana, and Firman. (2022). "Analisis Manajemen Pengadaan Material Konstruksi di PT. Takenaka Indonesia." Journal of Industrial Engineering Vol 07 No. 2 88-100.

Widiarso, Anggi. (2010). Pengaruh Manajemen Material terhadap Produktifitas Kerja Proyek Konstruksi Gedung Bertingkat pada Pekerjaan Struktur. Skripsi, Depok: Universitas Indonesia

Downloads

Published

2024-05-31

How to Cite

Azzahra, P., & Respati, R. (2024). Analisa Pengaruh Manajemen Material Terhadap Produktivitas Kerja Pada Proyek Konstruksi Gedung Bertingkat Di Kota Palangka Raya: Analysis Of The Effect Of Material Management On Work Productivity In Multi-Storey Building Construction Projects In Palangka Raya City. Media Ilmiah Teknik Sipil, 12(2), 159–166. https://doi.org/10.33084/mits.v12i2.7323