Model Keputusan Terpadu Berbasis Risiko dan Akuntabilitas Data untuk Kebijakan Preservasi Jalan Nasional: Integrasi Prediksi IRI-PCI, Earned Value Management, dan Unit Cost IRMS Pada Koridor Makassar-Parepare An Integrated Decision Model Based On Risk and Data Accountability for National Road Preservation Policy: Integration Of IRI-PCI Prediction, Earned Value Management, and IRMS Unit Cost On The Makassar-Parepare Corridor
Main Article Content
Abstract
Indonesia's national road management remains heavily reactive: segments are typically left to deteriorate until damage becomes visually evident before entering the maintenance program. This study proposes an integrated decision model linking road condition prediction, risk mapping, project performance, and data governance for the 155-km Makassar–Parepare national road corridor. Unlike prior analyses of the same dataset, which focused solely on correlation testing and regression, this study treats those statistical results as inputs to a comprehensive decision framework encompassing a technical-traffic-climate-budget-execution risk map, the relationship between road condition indicators and Ministerial Regulation No. 4/2023 on road functional eligibility, a strategy for strengthening the Pavement Management System (PMS) database, budget accountability mechanisms, and a five-stage implementation roadmap for BBPJN Sulawesi. The analysis draws on 26,818 observation segments (2020–2024), revealing a Pearson correlation of r = –0.2710 (p < 0.001) between IRI and PCI, and r = +0.1898 (p < 0.001) between IRI and AADT, alongside multiple regression models yielding R² = 0.1110 (IRI) and R² = 0.1053 (PCI). An Earned Value Management (EVM) evaluation of 50 projects worth IDR 65.08 billion shows an average CPI of 0.9758 and SPI of 0.9435. Findings indicate that execution risk, not physical deterioration risk alone, determines whether sound technical priorities translate into improved road conditions. The proposed integrated decision model comprises five stages—data integration, priority dashboarding, annual model calibration, IRMS-based budgeting, and EVM control—with an estimated 15–20% budget efficiency potential through preventive maintenance on segments with IRI 6–8 m/km, ahead of costlier reconstruction demand priced at IDR 1,923,900/m².
Downloads
Article Details

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
All rights reserved. This publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means, electronic, mechanical, photocopying, recording.
References
ASTM International (2023): Standard Practice for Roads and Parking Lots Pavement Condition Index Surveys (ASTM D6433-23), ASTM International, West Conshohocken, PA.
Ayuningtyas, F.H., Irawan, D., Suraji, A., dan Sudjianto, A.T. (2023): Penerapan metode earned value pada proyek peningkatan jalan di Kabupaten Jember, BOUWPLANK: Jurnal Ilmiah Teknik Sipil dan Lingkungan, 3(1), 36-42.
Balai Besar Pelaksanaan Jalan Nasional Sulawesi Selatan (2020-2024): Data kondisi jalan (IRI, PCI, AADT) koridor Makassar-Parepare, BBPJN Sulsel.
Badan Pusat Statistik Sulawesi Selatan (2020-2024): Jumlah kendaraan bermotor per kabupaten/kota dan PDRB per kapita di Sulawesi Selatan, BPS Sulsel.
Direktorat Jenderal Bina Marga (2024): Summary of Treatment Unit Cost - R08 Sulawesi Selatan (IRMS), Kementerian PUPR, Direktorat Jenderal Bina Marga, Jakarta.
Evans, M., Sumarwan, U., dan Hidayat, R.S. (2025): Analisis kondisi perkerasan jalan ruas Maros-Makassar menggunakan metode PCI dan IRI, JILMATEKS: Jurnal Ilmu dan Manajemen Teknik Sipil, 3(1), 389.
Hamedi, A., Yang, X., Zhang, Z., dan Rajagopalan, A. (2020): Leveraging long-term pavement performance database to investigate relationship between IRI and PCI, Transportation Research Record, 2674(7), 498-510.
Juliati, D., Mukhbir, A., dan Tahir, S. (2023): Analisis karakteristik curah hujan dengan menggunakan metode Schmidt-Ferguson di Kota Makassar periode 2012-2021, Jurnal Sains dan Pendidikan Fisika, 19(1).
Kementerian PUPR, Direktorat Jenderal Bina Marga (2024): Manual Desain Perkerasan Jalan 2024 (MDP 2024), Ditjen Bina Marga, Jakarta.
Kementerian PUPR (2023): Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Nomor 4 Tahun 2023 tentang Pedoman Laik Fungsi Jalan, Kementerian PUPR, Jakarta.
Kementerian PUPR, Direktorat Jenderal Bina Marga (2021): Pedoman Perencanaan dan Pemrograman Pekerjaan Preservasi Jaringan Jalan, Ditjen Bina Marga, Jakarta.
Llopis-Castelló, D., Moreno-Navarro, F., Rubio-Gámez, M.C., dan Montalban-Domingo, L. (2024): Contribution of connected vehicles data to road roughness monitoring: A systematic review, Transportation Research Part C, 161, 104578.
Proaño-Narváez, G.A., Ortega-Fierro, S.N., dan Torres-Jara, G.A. (2022): Earned value management implementation on road construction projects in Ecuador, Journal of Construction Engineering and Management, 148(3).
Qiao, Y., Dhulipala, S., dan Santos, J. (2025): IRI prediction model integrating PCI, distress types, climatic data and traffic data based on dual-model approach, Construction and Building Materials, 460, 139773.
Radwan, N., Khedr, S., dan Hassan, M. (2024): Correlation between pavement condition index and international roughness index for urban roads in arid climate, International Journal of Pavement Engineering, 25(1).
Saefudin, I., Darsana, I.W., dan Sudiasa, I.W. (2024): Analisis penilaian kondisi perkerasan jalan dengan metode PCI, SDI dan IRI, Syntax Idea, 6(4), 1870-1883.
Santosa, S., Siegfried, dan Kania, B. (2022): Identifikasi kebutuhan penanganan jalan berdasarkan nilai IRI dan PCI, Jurnal Indonesia Sosial Teknologi, 3(11), 1188-1204.
Sari, D., Sukmawati, S., dan Hasanuddin, A. (2023): Perbandingan nilai kerusakan jalan berdasarkan metode PCI dan metode IRI, Jurnal EXTRAPOLASI, 18(2), 67-78.
Sari, D.P. dan Salasa, B.S. (2023): Pengendalian waktu dan biaya dengan metode Earned Value Analysis: Studi kasus rekonstruksi jalan Kabupaten Kutai Kartanegara, Rekayasa Sipil, 17(3), 315-319.
Sa'dillah, M., Pandulu, G.D., dan Basri, M.H. (2024): Analisis kerusakan jalan berdasarkan metode IRI dan PCI, Jurnal Ilmiah Teknik Sipil, 12(2), 68-78.
Sitanggang, P.B., Mulia, A.P., dan Nasution, Z.P. (2022): Penerapan pavement management system (PMS) berbasis GIS untuk pemerintah daerah, Jurnal Teknik Sipil, 19(2), 145-158.
Styaji, H., Sobirin, M., dan Naibaho, P.R.T. (2026): Development of a predictive model for road maintenance management based on the correlation of IRI, PCI, and traffic data: A case study of earned value management implementation on the Makassar-Parepare corridor, ASTONJADRO, 15(4).
Yuliani, G., Hariyadi, E.S., dan Sjafruddin, A. (2025): Analisis pemrograman preservasi jalan dengan strategi penanganan sementara (back-fall strategy) skala jaringan menggunakan metode IRMS V.3 dan MEPDG 2015, Jurnal Teknik Sipil, 32(2).