Evaluasi Kinerja Pemeliharaan Waterproofing Rooftop Gedung IPU Menggunakan Metode EVM (Studi Kasus: RSUD dr. Saiful Anwar) Performance Evaluation Of Rooftop Waterproofing Maintenance At The IPU Building Using The EVM Method (Case Study: RSUD dr. Saiful Anwar)
Main Article Content
Abstract
Downloads
Article Details

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
All rights reserved. This publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means, electronic, mechanical, photocopying, recording.
References
Alkas, M. J., Sari, D. P., Haryanto, B., & Ramadanri, N. A. (2023). Pengendalian Biaya dan Waktu Proyek dengan Metode Analisis Nilai Hasil Menggunakan Microsoft Project (Vol. 1, Issue 1). DOI.
Alwarizi, F., Sari, S. N., & Hermawan, A. (2024). ANALISIS BIAYA DAN WAKTU DENGAN METODE NILAI HASIL PADA PROYEK PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI. 3(1), 80–88. https://doi.org/10.55123
Ardan, M., & Rahman Sidik Hasibuan, S. A. (2022). JURNAL TEKNIK SIPIL : RANCANG BANGUN Analisis Penerapan Manajemen Waktu Pada Proyek Pembangunan Gedung Rektorat dan Auditorium Akademi Pariwisata Medan. http://ejournal.um-sorong.ac.id/index.php/rancangbangun
Diasz, D., & Sarya, G. (2023). Evaluasi Biaya Dan Waktu Menggunakan Metode Earned Value Pada Proyek Pembangunan Saluran Drainase Di Jalan Pawiyatan, Kecamatan Bubutan, Kota Surabaya, Provinsi Jawa Timur. 8(2), 51.
Hussein, A. R., & Fard Moradinia, S. (2023). Mitigating Time and Cost Overruns in Construction Projects: A Questionnaire Study on Integrating Earned Value Management and Risk Management. Journal of Studies in Science and Engineering, 3(2), 37–51. https://doi.org/10.53898/josse2023323
Kamandang, Z. R., Dita, N., Putra, P., & Nauli, A. R. (2023). A Guideline of Earned Value Method (EVM) Implementation as Decision Baseline on Acceleration Solutions for Construction Project Scheduling. In Technium: Romanian Journal of Applied Sciences and Technology (Vol. 16). www.techniumscience.com
Muhammad Annas, F., Solikin, M., Rum Harnaeni, S., & Sunarjono, S. (2024). EVALUASI KINERJA BIAYA DAN WAKTU PELAKSANAAN MENGGUNAKAN METODE EARNED VALUE (EVM) (Studi Kasus: Proyek Pengendalian Banjir Kali Lamong).
Murdani Lubis, A., Suhendar, E., & Suharmanto, P. (2021). OPTIMASI PENJADWALAN PROYEK PEMBANGUNAN JALAN TOL BECAKAYU SEKSI 1BC DENGAN MENGGUNAKAN METODE CPM DAN PERT OPTIMIZING THE SCHEDULE OF THE BECAKAYU SECTION 1BC TOLL ROAD CONSTRUCTION PROJECT USING THE CPM AND PERT METHODS. In Universitas Sahid Jakarta.
Priyo, M. (2021). Earned Value Management System in Indonesian Construction Projects. International Journal of Integrated Engineering, 13(3), 37–45. https://doi.org/10.30880/ijie.2021.13.03.005
Purnomo, D. A., & Prisilia, H. (2024). Analisis Biaya Dengan Menggunakan EVM Pada Proyek Konstruksi (Studi Kasus : Proyek Rehabilitasi Mall Pelayanan Publik Kabupaten Banyuwangi).
Rodriguez, J. C. M., Pascual, J. L., Molina, P. C., & Márquez, F. P. G. (2017). An overview of earned value management in airspace industry. Advances in Intelligent Systems and Computing, 502, 1465–1477. https://doi.org/10.1007/978-981-10-1837-4_119
Sanjaya, H., & Johari, G. J. (2022). Analisis Optimalisasi Perencanaan Kembali Durasi dan Biaya Proyek menggunakan Metode Pertukaran Waktu dan Biaya. https://jurnal.itg.ac.id/
Sentana, H. S., Kurniawan Suksmono, A., Ayu, C., & Sari, N. (2024). Evaluasi Waktu Dan Biaya Menggunakan Earned Value Method (EVM) Pada Gedung Mal Pelayanan Publik (MPP) Kota Tegal. Jurnal Teknik Sipil Dan Bangunan. https://doi.org/10.32699
Siregar, A. C., & Iffiginia, I. (2019). Penggunaan critical path method (CPM) untuk evaluasi waktu dan biaya pelaksanaan proyek. Teknika: Jurnal Sains Dan Teknologi, 15(2), 102. https://doi.org/10.36055/tjst.v15i2.6816
Sofia, D. A., Wildan, M., & Yusdinar, H. (2022). ANALISIS KINERJA PROYEK PEMBANGUNAN GEDUNG MENGGUNAKAN KONSEP EARNED VALUE. Jurnal Ilmiah Teknik Sipil, 4.
Wicaksono, M. H., Sugandi, R. M., & Alfianto, I. (2024). Pengendalian Durasi Optimal pada Pembangunan Myze Hotel Sumenep Menggunakan CPM dan Metode PERT. Bentang : Jurnal Teoritis Dan Terapan Bidang Rekayasa Sipil, 12(1), 49–62. https://doi.org/10.33558/bentang.v12i1.7323
Widodo, S., Asriadi, A., Sutiono, W., Desembardi, F., Fauzi, H. N., & Fajar, M. N. (2023). Optimalisasi Biaya dan Waktu Pekerjaan Perumahan Griya Pekerja Sejahtera. Konstruksia, 15(1), 27. https://doi.org/10.24853/jk.15.1.27-33