Evaluasi Kinerja Pemeliharaan Waterproofing Rooftop Gedung IPU Menggunakan Metode EVM (Studi Kasus: RSUD dr. Saiful Anwar)

Performance Evaluation Of Rooftop Waterproofing Maintenance At The IPU Building Using The EVM Method (Case Study: RSUD dr. Saiful Anwar)

Authors

  • Nadine Marwa Savitri program studi teknik sipil s2 universitas negeri malang
  • Imam Alfianto Program Studi S2 Teknik Sipil, Fakultas Teknik, Universitas Negeri Malang

Keywords:

Earned Value Management, project performance evaluation, cost control, time control, infrastructure project

Abstract

Public construction projects often face challenges in controlling time and cost, including the maintenance project of the rooftop waterproofing of the IPU Building, 7th Floor, at RSUD Dr. Saiful Anwar, Malang City. This study aims to evaluate the project performance using the Earned Value Management (EVM) method, which integrates schedule and cost analysis to provide a comprehensive overview of project execution efficiency. The study was conducted up to the 5th week, with a work progress of 20.017%. The data used include the budget plan, S-curve, weekly reports, and actual project costs, analyzed using Microsoft Excel. The calculation results show that in the 4th week, the project experienced a cost deviation with a Cost Variance (CV) of -Rp47,228,379.15 and a schedule deviation with a Schedule Variance (SV) of -Rp16,025,142.49. The Cost Performance Index (CPI) of 0.76 indicates budget overrun, while the Schedule Performance Index (SPI) of 0.90 indicates a delay in execution. The estimated total cost at completion (EAC) is Rp939,260,546.02, exceeding the initial budget of Rp715,408,147.00, and the estimated total time for completion (EAS) is 9.42 weeks compared to the original plan of 9 weeks. These findings highlight the importance of implementing EVM to detect early project deviations and provide a quantitative basis for project performance evaluation

Downloads

Author Biography

Imam Alfianto, Program Studi S2 Teknik Sipil, Fakultas Teknik, Universitas Negeri Malang

Dosen, Program Studi S2 Teknik Sipil, Fakultas Teknik, Universitas Negeri Malang

References

Alkas, M. J., Sari, D. P., Haryanto, B., & Ramadanri, N. A. (2023). Pengendalian Biaya dan Waktu Proyek dengan Metode Analisis Nilai Hasil Menggunakan Microsoft Project (Vol. 1, Issue 1). DOI.

Alwarizi, F., Sari, S. N., & Hermawan, A. (2024). ANALISIS BIAYA DAN WAKTU DENGAN METODE NILAI HASIL PADA PROYEK PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI. 3(1), 80–88. https://doi.org/10.55123

Ardan, M., & Rahman Sidik Hasibuan, S. A. (2022). JURNAL TEKNIK SIPIL : RANCANG BANGUN Analisis Penerapan Manajemen Waktu Pada Proyek Pembangunan Gedung Rektorat dan Auditorium Akademi Pariwisata Medan. http://ejournal.um-sorong.ac.id/index.php/rancangbangun

Diasz, D., & Sarya, G. (2023). Evaluasi Biaya Dan Waktu Menggunakan Metode Earned Value Pada Proyek Pembangunan Saluran Drainase Di Jalan Pawiyatan, Kecamatan Bubutan, Kota Surabaya, Provinsi Jawa Timur. 8(2), 51.

Hussein, A. R., & Fard Moradinia, S. (2023). Mitigating Time and Cost Overruns in Construction Projects: A Questionnaire Study on Integrating Earned Value Management and Risk Management. Journal of Studies in Science and Engineering, 3(2), 37–51. https://doi.org/10.53898/josse2023323

Kamandang, Z. R., Dita, N., Putra, P., & Nauli, A. R. (2023). A Guideline of Earned Value Method (EVM) Implementation as Decision Baseline on Acceleration Solutions for Construction Project Scheduling. In Technium: Romanian Journal of Applied Sciences and Technology (Vol. 16). www.techniumscience.com

Muhammad Annas, F., Solikin, M., Rum Harnaeni, S., & Sunarjono, S. (2024). EVALUASI KINERJA BIAYA DAN WAKTU PELAKSANAAN MENGGUNAKAN METODE EARNED VALUE (EVM) (Studi Kasus: Proyek Pengendalian Banjir Kali Lamong).

Murdani Lubis, A., Suhendar, E., & Suharmanto, P. (2021). OPTIMASI PENJADWALAN PROYEK PEMBANGUNAN JALAN TOL BECAKAYU SEKSI 1BC DENGAN MENGGUNAKAN METODE CPM DAN PERT OPTIMIZING THE SCHEDULE OF THE BECAKAYU SECTION 1BC TOLL ROAD CONSTRUCTION PROJECT USING THE CPM AND PERT METHODS. In Universitas Sahid Jakarta.

Priyo, M. (2021). Earned Value Management System in Indonesian Construction Projects. International Journal of Integrated Engineering, 13(3), 37–45. https://doi.org/10.30880/ijie.2021.13.03.005

Purnomo, D. A., & Prisilia, H. (2024). Analisis Biaya Dengan Menggunakan EVM Pada Proyek Konstruksi (Studi Kasus : Proyek Rehabilitasi Mall Pelayanan Publik Kabupaten Banyuwangi).

Rodriguez, J. C. M., Pascual, J. L., Molina, P. C., & Márquez, F. P. G. (2017). An overview of earned value management in airspace industry. Advances in Intelligent Systems and Computing, 502, 1465–1477. https://doi.org/10.1007/978-981-10-1837-4_119

Sanjaya, H., & Johari, G. J. (2022). Analisis Optimalisasi Perencanaan Kembali Durasi dan Biaya Proyek menggunakan Metode Pertukaran Waktu dan Biaya. https://jurnal.itg.ac.id/

Sentana, H. S., Kurniawan Suksmono, A., Ayu, C., & Sari, N. (2024). Evaluasi Waktu Dan Biaya Menggunakan Earned Value Method (EVM) Pada Gedung Mal Pelayanan Publik (MPP) Kota Tegal. Jurnal Teknik Sipil Dan Bangunan. https://doi.org/10.32699

Siregar, A. C., & Iffiginia, I. (2019). Penggunaan critical path method (CPM) untuk evaluasi waktu dan biaya pelaksanaan proyek. Teknika: Jurnal Sains Dan Teknologi, 15(2), 102. https://doi.org/10.36055/tjst.v15i2.6816

Sofia, D. A., Wildan, M., & Yusdinar, H. (2022). ANALISIS KINERJA PROYEK PEMBANGUNAN GEDUNG MENGGUNAKAN KONSEP EARNED VALUE. Jurnal Ilmiah Teknik Sipil, 4.

Wicaksono, M. H., Sugandi, R. M., & Alfianto, I. (2024). Pengendalian Durasi Optimal pada Pembangunan Myze Hotel Sumenep Menggunakan CPM dan Metode PERT. Bentang : Jurnal Teoritis Dan Terapan Bidang Rekayasa Sipil, 12(1), 49–62. https://doi.org/10.33558/bentang.v12i1.7323

Widodo, S., Asriadi, A., Sutiono, W., Desembardi, F., Fauzi, H. N., & Fajar, M. N. (2023). Optimalisasi Biaya dan Waktu Pekerjaan Perumahan Griya Pekerja Sejahtera. Konstruksia, 15(1), 27. https://doi.org/10.24853/jk.15.1.27-33

Downloads

Published

2025-05-31

How to Cite

Nadine Marwa Savitri, & Alfianto, I. (2025). Evaluasi Kinerja Pemeliharaan Waterproofing Rooftop Gedung IPU Menggunakan Metode EVM (Studi Kasus: RSUD dr. Saiful Anwar): Performance Evaluation Of Rooftop Waterproofing Maintenance At The IPU Building Using The EVM Method (Case Study: RSUD dr. Saiful Anwar). Media Ilmiah Teknik Sipil, 13(2), 86–97. Retrieved from https://journal.umpr.ac.id/index.php/mits/article/view/9651