Perhitungan Produktivitas Tenaga Kerja Pasangan Dinding Bata Pada Proyek Perumahan di Kota Banjarmasin Calculation Of Labor Productivity Of Brick Wall Makers in Housing Projects in Banjarmasin City
Main Article Content
Abstract
Labor productivity is a crucial factor influencing the success of construction projects regarding cost, schedule, and work quality. This study aims to analyze labor productivity for red brick masonry and wall plastering tasks in a Banjarmasin housing project, compare productivity levels between morning and afternoon shifts, and evaluate the results against the 2026 Unit Price Analysis (AHSP) standards. A time study method—involving direct observation of labor activities—was employed to determine standard times and productivity rates. Primary data were collected through field surveys conducted between May and June 2026. The results indicate that brick masonry productivity was 0.899 m²/man-hour in the morning and 0.811 m²/man-hour in the afternoon, representing a 9.789% decrease. For brick wall plastering, productivity was 0.854 m²/man-hour in the morning and 0.816 m²/man-hour in the afternoon, a decrease of 4.450%. Given the AHSP 2026 standard of 0.768 m²/man-hour, field productivity for brick masonry was 5.597%–17.041% higher, while plastering productivity was 6.192%–11.242% higher than the standard. The findings demonstrate that the time of day influences labor productivity, with morning productivity levels exceeding those observed in the afternoon.
Downloads
Article Details

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
All rights reserved. This publication may be reproduced, stored in a retrieval system, or transmitted in any form or by any means, electronic, mechanical, photocopying, recording.
References
Albani Musyafa, S. T. (2021). Analisis Produktivitas Tukang Dan Harga Satuan Pekerjaan Pasangan Dinding Bata Merah Dan Bata Ringan. Universitas Islam Indonesia, Yogyakarta.
Analisa Harga Satuan Pekerjaan (AHSP) Bidang Cipta Karya (2026). Surat Edaran Direktur Jenderal Bina Konstruksi Nomor 47/SE/Dk/2026 Tentang Tata Cara Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum. Kementerian Pekerjaan Umum
Ervianto, Wulfram I. 2005. Manajemen Proyek Konstruksi. Andi, Yogyakarta.
Mahdy, A. H., Abma, V. (2024). Analisis Produktivitas Tukang Batu Bata Pada Pekerjaan Dinding Bata Merah. Universitas Islam Indonesia, Yogyakarta.
Narayana, I. (2024). Studi Kasus Produktivitas Tenaga Kerja Pada Pengerjaan Pasangan Dinding Menggunakan Bata Merah Konvensional Proyek Pembangunan Stas Villa Pererenan. Politeknik Negeri Bali.
Olomolaiye, P., Jayawardane, A., & Harris, F. (1998). Construction Productivity Management. Prentice Hall, London.
Sambolangi, D., Latupeirissa, J. E., & Tiyouw, H. C. P. (2024). Analisis Perbandingan Produktivitas Tukang Pada Pekerjaan Pasangan Dinding Bata Merah di Proyek Dengan SNI (Studi Kasus Proyek Pembangunan Perumahan Esa Garden Residence). Paulus Civil Engineering Journal, 6(2), 188-195.
Sigit, A. (2020). Perbandingan Produktivitas Pekerjaan Pasangan Dinding Bata Ringan Dan Bata Merah. Program Studi Teknik Sipil.
Yuliamora, D. (2024). Analisis Perbandingan Koefisien ProduktifitasTenaga Kerja Di Lapangan Dengan Koefisien Tenaga Kerja Pada AHSP 2016 Pada Pekerjaan Bata Merah. Jurnal Ilmiah Mahasiswa Teknik [JIMT], 4(2), 141-147.